The Central Aid Hong Kong Emergency Hospital & Lok Ma Chau shelter facilities were fully completed

May 23, 2022

    After 51 days and nights of hard work, the Central Aid Hong Kong Emergency Hospital and the Lok Ma Chau shelter facility have been fully completed recently, and the completion and delivery ceremony was officially held.

latest company news about The Central Aid Hong Kong Emergency Hospital & Lok Ma Chau shelter facilities were fully completed  0

    More than 20,000 people fought day and night, turning a deserted beach into a "Continent of Life"!

   

    China's infrastructure has once again exerted its strength and created a new miracle again. This miracle belongs to every sweaty builder, every hard-working engineer, and, of course, every enterprise who has given his best during this period...

    As a leading company in the domestic sealant industry, BAIYUN has participated in the construction of the Central Aided Hong Kong Emergency Hospital and Lok Ma Chau shelter facilities, and has worked hand in hand with various enterprises to provide mature and professional solutions for more than 90% of the project's bonding and sealing needs. , meticulous solutions, and make every effort to ensure the completion of the project on time.

latest company news about The Central Aid Hong Kong Emergency Hospital & Lok Ma Chau shelter facilities were fully completed  1

    When the project was completed, BAIYUN received letters of thanks from various cooperative enterprises.

   

    The aided construction project located in the Lok Ma Chau Loop area of Hong Kong includes three parts: the Central Aid Hong Kong Emergency Hospital, the Central Aid Hong Kong Lok Ma Chau Shelter Facility, and Living Supporting Facilities, with a total land area of about 500,000 square meters and a total construction area of about 283,100 square meters Meter.

    The Central Aid Hong Kong Emergency Hospital is a respiratory infectious disease specialist hospital approved by the Party Central Committee at the request of the Hong Kong Special Administrative Region Government. It can provide 1,000 negative pressure beds (including 100 ICU beds), 3 operating rooms and a radiology department. Laboratory, central supply room, blood transfusion and other medical and technical facilities, as well as supporting facilities such as drug storehouse, air compressor room, oxygen station, washing workshop, temporary garbage storage room, negative pressure traction pump room, and sewage treatment station.

latest company news about The Central Aid Hong Kong Emergency Hospital & Lok Ma Chau shelter facilities were fully completed  2

    The central aided Hong Kong Lok Ma Chau shelter isolation facility has a construction area of 112,100 square meters, can provide 10,056 beds, and includes an admission building, a discharge building, a sanitary passage area, an inspection center and CT room, a warehouse and a pharmacy, and a sub-control center convergence computer room , medical waste station, sewage treatment station and other supporting facilities.

latest company news about The Central Aid Hong Kong Emergency Hospital & Lok Ma Chau shelter facilities were fully completed  3

    The construction of the Central Aid Hong Kong Emergency Hospital started on March 6, 2022, and was completed and accepted on April 20. The construction of the Lok Ma Chau shelter facility started on March 22 and was completed and accepted on April 25. The two projects lasted 51 days, once again demonstrating the strong strength of China's infrastructure.

    Previously, BAIYUN assisted in the construction of additional isolation facilities in Hong Kong Penny's Bay, Hong Kong Kai Tak additional isolation facilities, Shenzhen Baguang Isolation Hotel, Shenzhen Changda International Hotel (Shajing Street New Coronary Pneumonia Epidemic Prevention and Control Isolation Hotel) and Guangzhou International Health Station We have accumulated a lot of experience in epidemic prevention projects. During the construction of this project, BAIYUN gave full play to its technical advantages and speed advantages, measured the needs of the project immediately, and provided adhesive solutions for multi-field sealing systems including curtain walls, doors and windows, roofs, and interior decoration for the project construction. Program.

    In response to the problems of many details and nodes, large volume, tight construction period, and heavy tasks in the project, BAIYUN communicated with the construction team many times to ensure smooth product transportation lines and ensure the orderly supply of products on the project at the first time. During the application period, with stable product quality and thoughtful whole-process service, BAIYUN brand products have passed the pre-construction adhesion test and compatibility test at one time. In the construction stage, one-time glue application is ensured, no rework is required, and the time is minimized. Run for life.